Bellmawr Landfill Warehouse Groundbreaking; Three Buildings, 1 Million+ Square Feet

Greystar, in conjunction with the Borough of Bellmawr, has announced groundbreaking for Big Timber Junction Logistics Park, a three-building warehouse development totaling more than one million square feet at the former landfill along Big Timber Creek.

The 150-acre property at 744 Creek Road will also feature a roughly 40-acre public waterfront park and a 1.1-mile walking trail. As previously reported by 42Freeway, that recreational component will give residents an opportunity to experience a beautiful stretch of waterfront that has long been difficult to access.

Greystar and Bellmawr announced ground has been broken on a 3 warehouse project at the former Bellmawr/Deptford landfill along Route 42 and I-295.

Greystar appears ready to move fast on this project, announcing the groundbreaking October 22nd, with project completion targeted for First Quarter 2028 which is less than 18-months for the development. Along with the groundbreaking, they’ve announced the company has taken ownership of the multiple parcels that make up the development site (County property records have not been posted yet so financials are not known at this time)

Most South Jersey commuters likely recognize this property from its high hills visible off to the right when traveling south on Route 42 through Bellmawr. The property also extends along local Creek Road.

Dirt/Gravel foundation pads are already in place for the warehouse sites. This center one.. actually in Deptford!

Over the last 20 years this property was proposed as a variety of efforts that did not come to fruition including a massive mixed-use housing and retail complex, a Bass Pro Shops, Sports arena and more. To be clear.. three warehouses appear to be the final plan.

While building construction for the warehouses had not previously started, substantial dirt work has been visible for some time, establishing the foundations for the development.

An interesting aspect is that the crescent-shaped property spans two municipalities. The two outer portions are in Bellmawr, while the middle is in Deptford. That unusual boundary follows the historic path of Timber Creek before the landfill existed.

The development places two warehouses in Bellmawr and one in Deptford.

The raised hill to the right of Route 42 South in Bellmawr is well known to commuters and will soon feature a large warehouse.

Accessory Benefits

Alongside the announcement, Bellmawr published a presentation Greystar recently delivered to the mayor and borough council, outlining construction, infrastructure, and financial details.

According to that presentation, the landfill has undergone more than 20 years of remediation under New Jersey Department of Environmental Protection oversight. Construction of Big Timber Junction will complete the cap required for landfill closure, allowing the property to move into productive use.

Diagram of the upcoming Leaf Avenue Extension project. Roadway changes in Yellow.

The project also ties into an upcoming reconfiguration of Leaf Avenue and its connection to Route 42 South, which 42Freeway covered in August.

For the Leaf Avenue project, it will shift the main traffic signal and Route 42 entry point west down Creek Road, with the goal of reducing local traffic backups around Harding Avenue and Wawa, while also creating a more formal entrance into the logistics park.

The waterfront park and trail are expected to open in the third quarter of 2027. The Leaf Avenue extension and connector road are scheduled for completion by the end of 2027, followed by the logistics park in early 2028.

The upcoming Big Timber Creek waterfront park and trail

Three Warehouses and PILOT Payments

The three buildings total 1,001,010 square feet:

  • Building A: 406,309 square feet, with cross-dock loading, 451 feet depth, 40-foot clear height, 93 dock doors, four drive-in doors, 155 trailer spaces, and 302 car parking spaces.
  • Building B: 345,272 square feet, with 36-foot clear height, 55 dock doors, two drive-in doors, 36 trailer spaces, and 314 car parking spaces.
  • Building C: 249,429 square feet, with 36-foot clear height, 45 dock doors, two drive-in doors, and 215 car parking spaces.

Check with Greystar or CBRE reality for more details.

The presentation indicates all three buildings will be delivered within months of one another, with Building B expected ahead of the final building.

The project will make payments through a PILOT agreement, with projected annual payments of approximately $1.4 million in years one through five, increasing to $2.2 million in years 26 through 30.

Payments will be divided between Bellmawr and Deptford based on building square footage under their financial agreements. The order in which buildings open could initially affect how much each municipality receives although Greystar states the three warehouse will be developed at the same time (but slightly staggered in completion time).

Greystar Managing Director for Development George Hayward said the location positions the project to serve regional distribution, last-mile fulfillment, and port-related operations.

At this time, it appears no tenants have been announced. CBRE will handle leasing.

Mostly inaccessible to residents (except the very few with boats), the Big Timber Creek in Bellmawr/Deptford will soon have plenty of access with a new waterfront park and trail.

Links and Location

Bellmawr Redevelopment – Waterfront Park and Trail
Creek Road
Bellmawr NJ

Leave a Comment